top of page
tatsuki construction,Tatsuki Construction Co., Ltd.
涌谷太陽光発電所

Construction work of Solar power plant in Wakuya

​ Wakuya solar power plant construction work

Construction site Wakuya Town, Toda District, Miyagi Prefecture

Construction area 49.8 ha.

Construction amount Cut amount 684,300 m3 Filling amount 689,540 m3

​ Completion of construction work December 2nd year of Reiwa

涌谷太陽光発電所造成工事
伐採 測量 涌谷

Logging / Logging / Rooting

Before starting the construction work, trees such as cedar and cypress will be cut down and taken out of the site for resource recovery. We will carry out construction while surveying so as not to cut down the remaining green space.

ブルドーザー 押土 敷均し 涌谷

​ Earthworks Bulldozer construction

​ We will excavate and transport soil with a bulldozer.

アーティキュレートダンプ

Dump truck

​30t Transport the soil with an arculate dump truck.

掘削 運搬 敷均し

​ Earthworks Dump truck Backhoe excavation Leveling

​ Soil is loaded into the dump truck with a backhoe, transported, and leveled and compacted with a bulldozer.

掘削 運土 調整池 

​ Retention basin excavation, slope shaping, rock crushing

​ We will excavate with a backhoe while shaping the slope of the regulating pond. When a hard bedrock appears, excavate it while crushing it with a breaker.

調整池 50tクレーン

Retention basin drainage tower installation

We will construct a drainage tower for the regulating pond. This is a 2.1m square drainage tower with a height of 5.7m. The box culvert to be connected is 1.6m square and has an extension of 33.6m.

涌谷太陽光発電所 伐採工事 土工事

​Overview Photograph of the start of construction work

The logging work has been completed and the construction work has begun. The regulating pond will be created first, the slope will be set as planned, and the cut and embankment will be constructed.

涌谷太陽��光発電所 完成

Photograph of the completed view

The construction work was completed successfully, solar panels were installed, and the power plant was put into operation.

Ⓒ TATSUKI-CONSTRUCTION.ALL RIGHTS RESERVED.

bottom of page